Leveraging BIM, Reality Capture & AR/VR for Infrastructure Project Success: A Case Study
Problem Statement from the client
The client was coming up with an internal road infrastructure project with utilities. The problem here was their design team was working on 2d drawings and the client's goal was to implement the complete digital framework for this project and implement the latest innovation technologies. Some of the requirements from the client are to Develop the 3D model, Implement the coordination activities and resolve the clashes frontend, Implement 4D simulation, and track the project with reality capture technology. Implement augmented and virtual reality technologies to show the infrastructure to their investors.
Scope of Work
The solution provided to meet the goal and requirements of client was “BIM, DPM using Reality capture & AR/VR for infrastructure project” which included:
During Detail design Phase
During the Construction Phase
Project Location:
Bangalore, India.
Input Shared by the client:
Software used:
Project Timeline:
Key Challenges & How we solved the problem:
Breaking down the BIM model to match with the project schedule Work breakdown structure was challenging for certain 3d elements.
Solution:
Certain elements cannot be broken down like electrical & water chambers, sewer manholes etc. so we have developed the model inline with work breakdown structure for better simulation and tracking project progress.
Selecting and Linking the 3d model to all the activities was quite challenging and the project schedule was not the level to show the virtual constructability simulation.
Solution:
First we broke down the schedule to one more level in WBS for better virtual construction simulation and tracking. A unique WBS ID was generated and assigned to the 3d elements, this activity saved a lot of time in linking the model to the project schedule for virtual construction simulation.